In February 2017, following recent bolt failures experienced with both Vetco H4 and Cameron Collet connectors, attributed to hydrogen embrittlement of H4 connector bolts, API released a new bolting specification - API Spec 20E for carbon steel (Available to Purchase from API).  An earlier version of API Spec 20F – Corrosion Resistant Bolting for Use in Petroleum & Natural Gas Industries, included specifications for stainless steel bolting.

This new specification, API Spec 20E, outlined the material specifications for 3 different levels of bolting. The new specifications are detailed and go extensively into the metallurgy of the bolts, including grain structure requirements post heat treatment.

ADC Virtual Academy

A BOP is a large set of specialised valves used for controlling and monitoring an oil or gas well.

Want to know more? ADCs Virtual Academy can provide training worldwide 24/7 on Drilling Equipment, IWCF level 2 Well Control, and Understanding Dropped Objects.

The main points which arise from this revision are that the fasteners used in BOP flanges (B7, L7, L44 etc.) have to conform to 3 Bolting Specification Levels – BSL’s (BSL-1, BSL-2 & BSL-3) and to meet API 20E or 20F, have to be stamped with 20E1 for BSL-1, 20E2 for BSL-2 or 20E3 for BSL-3 in addition to the already required B7, L7, L44 grade stamp and a unique heat code stamp is also a requirement.

ADC has over 30 years experience in Rig Inspection Worldwide

ADC has over 30 years experience in Rig Inspection worldwide.

Get in touch today to see how we can help you.

BACKGROUND

The latest edition of API Spec 16A (Available to Purchase from API) is the 4th edition (effective date 01 February 2018), inclusive of the Errata 1 - date of issue: August 2017. This revision of API 16A (with the inclusion of Errata 1) included a change to the effective date of the Specification from the 1st October 2017 to 1st February 2018.

BOP In moonpool

It is understood that this extension, given from October 2017 to February 2018, was to allow for contractor compliance, however they would have to be fully compliant by February 2018.

API Spec 20E and 20F are international specifications / standards and are stated as normative references within the fourth edition of API Spec 16A.

API 16A, Edition 4 released in April 2017 became effective as of the 1st October 2017 and this states what BSL the bolts of certain equipment are required to be. This is laid out in Table 6 (on page 21) for Land and offshore service.

(Above) A BOP in the moonpool area of the rig - bolts found on a BOP can range from a couple of inches to several feet long!

SUMMARY

In accordance with the latest revisions of API Spec 16 A, 20 E & 20 F, pressure retaining and closure bolting needs to meet API 20E & 20F BSL-3 specifications (on surface and subsea BOP’s) and for land use, pressure retaining and closure bolting needs to meet API 20E & 20F BSL-2 specifications.

For API Spec 20E compliance bolting was to be marked as follows:

  • '20E1' for BSL-1
  • '20E2' for BSL-2
  • '20E3' for BSL-3

This will impact the vast majority of every bolt/stud used on the BOP for all flanges, hubs and bonnet closure.

Now that these changes to API have been in place for some time, current BOPs inspected are still being found non-compliant with these Specs and are therefore highlighted as a non-conformance against the appropriate API specifications at the conclusion of our rig and BOP inspections.  There are a number of challenges faced by the industry as a whole including a shortage in supply of these bolts for the OEMs.  It is the responsibility of the Drilling Contractor to put in place a Management of Change to mitigate the risk of failure and ensure an ongoing change out process. This poses the real question – is your current BOP setup compliant?

Please stay in touch with ADC Americas for real examples of recent inspection findings, changes in legislation, OEM Bulletins and Industry updates that may have a direct impact to you and your operations.

Extract from API Spec 16 A, Specification for Drill-Through Equipment, 4th Edition, April 2017, Effective Date, 01 October 2017 – Table 6

ADC Provided further information on these changes in the following Drilling Contractor Article:  Planning, temporary mitigation critical for industry to effectively comply with revised API standards

Virtual Academy elearning is ADC's acclaimed online training product. To view our short presentation video click HERE

If you would like to subscribe to receive regular email updates about ADC Virtual Academy training click HERE

For more information about ADC products, services and their 30 years' experience in the Oil & Gas sector click  HERE